AlexRenew Celebrates Tunnel Completion on 'Hazel Day'

AlexRenew Celebrates Tunnel Completion on 'Hazel Day'

Hazel will dig a 12-foot-wide, 2-mile-long tunnel to divert approximately 120 million gallons of sewage annually away from Alexandria’s waterways.

In the summer of 2022, Treatment Plant Operator first reported on a new 380-ton, 14-foot 8-inch tall tunnel boring machine (TBM) named Hazel that had been unveiled by AlexRenew — Alexandria, Virginia’s wastewater authority — marking a significant milestone in its RiverRenew...

Please login or register to view TPO articles. It's free, fast and easy!


Discussion

Comments on this site are submitted by users and are not endorsed by nor do they reflect the views or opinions of COLE Publishing, Inc. Comments are moderated before being posted.